|
Additional Water
for the San Joaquin River Agreement,
2000 2010 Supplemental EIS/EIR
4. SURFACE WATER
RESOURCES
Index
4.1 AFFECTED ENVIRONMENT
This section of the Supplemental Environmental
Impact Statement/Environmental Impact Report (SEIS/EIR)
focuses on the surface waters of the San Joaquin
River Basin and the resulting flows from the basin
into the Delta as measured at the U.S. Geological
Survey gauging station on the San Joaquin River
near Vernalis. Details of the surface water resources
in the study area are described in Meeting Flow
Objectives for the San Joaquin River Agreement,
1999-2010, Final Environmental Impact Statement/Environmental
Impact Report (Final EIS/EIR, Reclamation 1999).
This section contains a summary of the water resources
in the study area with emphasis on those resources
directly related to the acquisition of "supplemental"
water.
The San Joaquin River Basin is contained within
the southern portion of the Central Valley of California.
The basin extends approximately 250 miles north-to-south,
encompasses about 32,000 square miles, and is bounded
by the Sierra Nevada mountains on the east and the
Diablo Range on the west. Extensive water supply,
hydroelectric, and flood control efforts during
the past century have resulted in the construction
of dams and reservoirs that now control the flow
on nearly all major streams in the San Joaquin River
Basin.
4.1.1 Surface Water
in the San Joaquin River Basin
The primary sources of surface water to the San
Joaquin River Basin are rivers that drain the western
slope of the Sierra Nevada Range. Each of these
rivers, the San Joaquin, Merced, Tuolumne, Stanislaus,
Calaveras, Mokelumne, and Cosumnes, drains large
areas of high elevation watershed that supply snowmelt
runoff during the late spring and early summer months.
Historically, peak flows occurred in May and June
and flooding occurred in most years along all of
the major rivers. The only rivers considered in
this document as sources of supplemental water are
the Merced and the Tuolumne rivers. The other rivers
in the basin are not discussed. The Final EIS/EIR
provides additional information.
4.1.2 Upper San Joaquin
River and Tributaries
The San Joaquin River originates in the Sierra
Nevada at an elevation above 10,000 feet and flows
into the San Joaquin Valley at Friant. Along the
valley floor, the San Joaquin River receives additional
flow from the Merced, Tuolumne, and Stanislaus rivers.
Flows in the upper San Joaquin River are regulated
by the Central Valley Project (CVP) Friant Dam,
which was completed in 1941 to store and divert
water to the Madera and Friant-Kern canals for irrigation
and municipal and industrial water supplies in the
eastern portion of San Joaquin Valley. Releases
from Friant Dam are generally limited to those required
to satisfy downstream water rights. Millerton Lake,
formed by Friant Dam, has a capacity of 520,000
acre-feet.
4.1.3 Lower San Joaquin
River and Tributaries
The lower San Joaquin River is the section of river
from the confluence with the Merced River (below
Fremont Ford) to Vernalis, which is generally considered
the southern limit of the Delta. It is characterized
by the combination of flows from tributary streams,
major rivers, groundwater accretions, and agricultural
drainwater. The drainage area of the San Joaquin
River above Vernalis is approximately 13,356 square
miles. However, little water is contributed from
the upper San Joaquin River, except during flood
events. Therefore, flows in the lower San Joaquin
River are primarily governed by the tributary inflows
from the Merced, Tuolumne, and Stanislaus rivers.
4.1.3.1 Merced River
The Merced River drains an area of approximately
1,273 square miles east of the San Joaquin River,
and produces an average unimpaired runoff of approximately
1 million acre-feet. The major water supply reservoir
on the river is Lake McClure, with a capacity of
1,024,000 acre-feet. It is formed by New Exchequer
Dam, completed in 1967, which regulates releases
to the lower Merced River. New Exchequer Dam is
owned and operated by the Merced Irrigation District
(Merced ID) for power production, irrigation, and
flood control.
4.1.3.2 Tuolumne River
The Tuolumne River drains a watershed of approximately
1,540 square miles, and produces an average annual
unimpaired runoff of approximately 1.8 million acre-feet.
Flows in the lower portion of the Tuolumne River
are controlled primarily by the operation of New
Don Pedro Dam, which was constructed in 1971 jointly
by the Turlock Irrigation District (TID) and the
Modesto Irrigation District (MID) with participation
by the City and County of San Francisco (CCSF).
The 2.03-million-acre-foot reservoir stores water
for irrigation, hydroelectric generation, fish and
wildlife enhancement, recreation, and flood control
purposes.
4.1.3.3 Stanislaus River
The Stanislaus River drains a watershed of approximately
900 square miles, and produces an average unimpaired
runoff of approximately 1.056 million acre-feet.
Flows in the lower Stanislaus River are controlled
by releases from the New Melones Reservoir, which
has a capacity of 2.4 million acre-feet, and is
operated by the U.S. Bureau of Reclamation (Reclamation)
as part of the CVP. The main water diversion point
on the Stanislaus River is Goodwin Dam, which provides
for delivery to Oakdale and South San Joaquin irrigation
districts.
4.1.3.4 San Joaquin River
at Vernalis
Flows in the San Joaquin River at Vernalis are
affected by the operation of upstream facilities
on the San Joaquin, Merced, Tuolumne, and Stanislaus
rivers, as well as by deliveries to the Mendota
Pool from the Delta-Mendota Canal and overflows
from the Kings River in the Tulare Lake Region.
Prior to the construction of major dams on the San
Joaquin River and its tributaries, average monthly
flows peaked during May and June in response to
snowmelt runoff. Unrestricted flows have not occurred
since the construction of the original Exchequer
and Don Pedro reservoirs in the 1920s. Flows in
the San Joaquin River near Vernalis have been further
altered from natural conditions by the completion
of Friant Dam in 1941, New Exchequer Dam in 1967,
New Don Pedro Dam in 1971, and New Melones Dam in
1978. Since 1978, average monthly flows in the San
Joaquin River at Vernalis have been more uniform
throughout the year, with maximum flows less than
historical levels.
4.1.4 Surface Water Quality
in the San Joaquin River Basin
Surface water quality in the San Joaquin River
Basin is affected by several factors, including
natural runoff, agricultural return flows, biostimulation,
construction, logging, grazing, operations of flow
regulating facilities, urbanization, and recreation.
In addition, irrigated crops grown in the western
portion of the San Joaquin Valley have accelerated
the leaching of minerals from soils, altering water
quality conditions in the San Joaquin River system.
Water quality in the San Joaquin River varies considerably
along the streams length. In the reaches above
Millerton Lake, water quality is generally excellent.
However, there are several reaches of the river
below Friant Dam that are often dry due to the groundwater
percolation. From Salt Slough to Fremont Ford, most
of the flow in the river is derived from irrigation
returns carried by Salt and Mud sloughs. This reach
of the San Joaquin River typically has the poorest
water quality of any reach of the river.
As the San Joaquin River progresses downstream
from Fremont Ford, water quality generally improves
at successive confluences, specifically at those
with the Merced, Tuolumne, and Stanislaus rivers.
In the relatively long reach between the Merced
and Tuolumne rivers, however, mineral concentrations
tend to increase due to agricultural drainwater
return flows, other wastewaters, and effluent groundwater
(DWR 1965 as cited in Reclamation 2000a). Total
dissolved solids (TDS) in the San Joaquin River
near Vernalis has historically ranged from 52 milligrams
per liter (mg/L) (at high stages) to 1,220 mg/L
during the period from 1951 to 1962 (DWR 1965 as
cited in Reclamation 2000a). In 1978, the State
Board included a provision in Water Right Decision
1422 (State Board 1978) that Reclamation maintain
average monthly concentrations of TDS in the San
Joaquin River at Vernalis of 500 mg/L as a condition
of the operating permit for New Melones Reservoir
on the Stanislaus River. In the Water Control
Quality Plan for the San Francisco Bay and Sacramento-San
Joaquin Delta Estuary (1995 WQCP, State Board
1995a) the water quality objective is expressed
as a seasonal 30-day running average value of electrical
conductivity. For the period April through August,
the objective is 0.7 mmhos/cm and the objective
is 1.0 mmhos/cm the remainder of the year. (This
corresponds to TDS concentrations of 427 and 610
mg/L.)
4.1.5 Water Facilities and
Operations
4.1.5.1 Central Valley Project
Facilities and Operations
The CVP is the largest surface water storage and
delivery system in California, with a geographic
scope covering 35 of the state's 58 counties. The
project includes 20 reservoirs, with a combined
storage capacity of approximately 11 million acre-feet;
8 powerplants and 2 pump-generating plants, with
a combined generation capacity of approximately
2 million kilowatts; 2 pumping plants; and approximately
500 miles of major canals and aqueducts. The CVP
supplies water to more than 250 long-term water
contractors in the Central Valley, the Santa Clara
Valley, and the San Francisco Bay Area.
Historically, approximately 90 percent of the CVP
water has been delivered to agricultural users,
including senior water rights holders. Total annual
contracts exceed 9 million acre-feet, including
over 1 million acre-feet of Friant Division Class
II supply, which is generally available only in
wet years.
CVP operations are influenced by a myriad of general
operating rules, regulatory requirements, and facility-specific
concerns and requirements. A summary of the operations
of the CVP is provided in the Final EIS/EIR (Section
3.2.5.1, Reclamation 1999) and is not repeated here.
The Eastside Division of the CVP includes water
storage facilities on the Stanislaus River (New
Melones Dam, Reservoir, and Powerplant), Chowchilla
River (Buchanan Dam and Eastman Lake), and Fresno
River (Hidden Dam and Hensley Lake). All of the
dams and reservoirs in this division were constructed
by the U.S. Army Corps of Engineers. Upon its completion
in 1978, the operation of New Melones Dam was assigned
to Reclamation to provide flood control, satisfy
water rights obligations, provide instream flows,
maintain water quality conditions in the Stanislaus
River and in the San Joaquin River at Vernalis,
and provide deliveries to CVP contractors.
The operating criteria for New Melones Reservoir
are governed by water rights, instream fish and
wildlife flow requirements, instream water quality,
Delta water quality, CVP contracts, and flood control
considerations. Flows in the lower Stanislaus River
serve multiple purposes. These include providing
water for instream water rights obligations, meeting
instream fishery flow requirements, maintaining
instream water conditions of dissolved oxygen, and
maintaining water quality conditions in the San
Joaquin River at Vernalis, in accordance with Water
Right Decisions 1422 and 1641, and the 1995 WQCP.
Water is also released from New Melones Reservoir
to meet, to the extent available, the San Joaquin
River flow requirements in the 1995 WQCP.
During the period from 1987 to 1992 New Melones
Reservoir was drawn down to approximately 80,000
acre-feet. Many Stanislaus River stakeholder meetings
were convened to coordinate management of limited
water supplies. Consequently, the May 1997 New Melones
Interim Operations Plan provides examples of operation
under the 50 percent (most probable) and 90 percent
probability of exceedance (90 percent chance of
having increased flows) hydrologic conditions which
include Water Years 1997 and 1998 (Reclamation 2000k).
This interim plan is currently the subject of stakeholder
refinement.
4.1.5.2 State Water Project
Facilities and Operations
State Water Project (SWP) facilities consist of
22 dams and reservoirs that capture and store water
on the Feather River, in order to deliver water
to service areas in the Feather River Basin, the
San Francisco Bay area, the San Joaquin Valley,
the Tulare Basin, and Southern California. Lake
Oroville, SWPs largest reservoir, with a storage
capacity of approximately 3.5 million acre-feet,
regulates the Feather River for release to Sacramento
River and the Delta. The water is diverted by various
facilities of the SWP for delivery to contractors
or salinity control. In addition, Lake Oroville
provides flood control, fish and wildlife habitat,
irrigation water, hydroelectric generation, and
recreation (Water Education Foundation 1997).
The SWP operates two diversion facilities in the
Delta. The North Bay Aqueduct diverts water from
the north Delta near Cache Slough for agricultural
and municipal uses in Napa and Solano counties.
In the southern portion of the Delta, the Banks
Delta Pumping Plant lifts water into the California
Aqueduct from the Clifton Court Forebay. The California
Aqueduct is the state's largest and longest water
conveyance system (444 miles), beginning at
the Banks Pumping Plant and extending to Lake Perris
south of Riverside, in Southern California. Water
in the California Aqueduct flows to ONeill
Forebay, from which a portion of the flow may be
lifted to the joint CVP/SWP San Luis Reservoir for
storage. From ONeill Forebay, the joint-use
portion of the aqueduct, San Luis Canal, extends
south to the southern end of the San Joaquin Valley.
The SWP portion of the aqueduct continues over the
Tehachapi Mountains to the South Coast Region.
About 30 percent of SWP water is used for irrigation,
mostly in the San Joaquin Valley. Approximately
70 percent is used for residential, municipal, and
industrial use, mainly in southern California. Currently,
the SWP has contracted a total of 4.22 million acre-feet
for delivery in San Joaquin River Region, the Central
Coast Region, and the San Francisco and South Coast
regions. Of this amount, about 2.5 million acre-feet
is designated for the Southern California Transfer
Area, nearly 1.36 million acre-feet to the San Joaquin
Valley, and the remaining 0.37 million acre-feet
to the San Francisco Bay area, the Central Coast
Region, and the Feather River area.
4.1.5.3 San Joaquin River
Group Authority Willing Sellers
Supplemental water for the Project would come from
willing sellers on either or both of the Merced
or Tuolumne rivers, up to a maximum of 47,000 acre-feet
from one or both rivers. Districts willing to supply
supplemental water for the Vernalis Adaptive Management
Plan (VAMP) Target Flow are the Merced ID, MID,
and TID. A brief discussion of these districts is
provided below.
Tuolumne River -
Modesto and Turlock Irrigation Districts
Tuolumne River water has been used for irrigation
in the Central Valley since the late 1890s, when
MID/TID constructed storage and conveyance facilities.
The water resources of the upper basin were developed
for water supply by the CCSF during the early decades
of the 20th century. This development
modified the natural flow regime of the Tuolumne
River; on average, more than 60 percent of the annual
flow has been diverted for agricultural or municipal
and industrial use. The three reservoirs in the
Hetch Hetchy System (not including storage in CCSFs
Don Pedro Water Bank) can store up to 35 percent
of the mean annual unimpaired flow of the river
as measured below La Grange. New Don Pedro Reservoir,
along with the two smaller district-specific storage
reservoirs (Modesto Reservoir and Turlock Lake),
can store up to 112 percent of the mean annual flow
of the river (FERC 1996).
The New Don Pedro Project (NDPP) is owned and operated
by the Districts and consists of the New Don Pedro
Dam, Don Pedro Reservoir (New Don Pedro Lake), and
the New Don Pedro Powerhouse. Diversions from the
NDPP system as well as from La Grange Dam, the TID
and MID diversion facilities at the La Grange Dam,
the TID canal system, TIDs Turlock Lake, the
MID canal system, and MIDs Modesto Reservoir
currently supply water to agricultural users. MID
began supplying Tuolumne River water to the city
of Modesto in 1995. NDPP also provides flood control,
hydropower production, reservoir-based recreation,
and fish and wildlife conservation.
The New Don Pedro Dam is an earth and rockfill
structure located at Tuolumne River mile 54.5. It
has a crest length of 2,300 feet and a maximum height
of 585 feet above the streambed. The dam was constructed
in 1971 to replace the original Don Pedro Dam, which
was located approximately 2 miles upstream. The
New Don Pedro Reservoir has a gross capacity of
2,030,000 acre-feet and a net usable capacity for
irrigation, flood control, and hydropower generation
(FERC 1996).
La Grange Dam is a diversion facility also owned
and operated by the Districts and is located 2.3
miles downstream of New Don Pedro Dam. The dam is
a 130-foot-high overflow structure built in 1893
and impounds approximately 500 acre-feet of water.
The Turlock Main Canal and the Modesto Main Canal
divert water from just above La Grange Dam into
an extensive network of irrigation canals on both
sides of the Tuolumne River, with TIDs canals
on the south and MIDs on the north. Both irrigation
districts have an intermediate storage reservoir
at the upper end of their canal network to help
regulate flows. Turlock Lake, on the south side
of the Tuolumne River, has a capacity of 48,000
acre-feet. Modesto Reservoir, on the north side
of the river, has a capacity of 28,000 acre-feet
(FERC 1996).
The Hetch Hetchy System is owned and operated by
CCSF and is not part of the FERC-licensed NDPP facilities.
CCSF regulates the upper portion of the Tuolumne
basin through the operation of its Hetch Hetchy
System for municipal and industrial water supply
and hydropower generation. Hetch Hetchy facilities
include OShaughnessy Dam at the Hetch Hetchy
Reservoir; the Hetch Hetchy Aqueduct; the Canyon
Power Tunnel; the Kirkwood Powerhouse; the Early
Intake Diversion Dam; and the Cherry Creek Power
Development. A portion of the storage in New Don
Pedro is allocated to CCSF through a water bank
arrangement (FERC 1996).
Merced River - Merced
Irrigation District
Flows in the Merced River are regulated primarily
by four major facilities: New Exchequer Dam (Lake
McClure), McSwain Reservoir and Powerplant, Merced
Falls Dam, and Crocker-Huffman Dam. The largest
reservoir, Lake McClure, has a capacity of 1,024,000
acre-feet and is created by New Exchequer Dam. Merced
ID owns and operates the reservoir for power, irrigation,
recreation and flood control purposes. Water released
from Lake McClure passes through a series of powerplants
and smaller diversions before reaching the main
diversion point. McSwain Reservoir, a part of Merced
IDs Merced River Development Project, serves
as an afterbay to New Exchequer Dam and Powerplant,
re-regulating power generation releases to the Merced
River. The capacity of McSwain Reservoir is 9,200
acre-feet (Merced ID 1997). Merced Falls Dam, from
which diversions are made to Merced IDs Northside
Canal, is owned and operated by PG&E. Downstream
of Merced Falls Dam is the Crocker-Huffman Dam,
from which diversions are made to Merced IDs
Main Canal. On average, just over 50 percent of
the annual streamflow in the Merced River below
Merced Falls Dam is diverted to Merced IDs
Main Canal (500,900 acre-feet per year between 1955
and 1980) (Merced ID 1997).
4.2 ENVIRONMENTAL CONSEQUENCES
AND MITIGATION MEASURES
This section evaluates the impacts of providing
supplemental water for VAMP during "double-step
years" as described in Chapter 2 of this SEIS/EIR
on surface water resources. During "double-step"
years, up to 47,000 acre-feet of supplemental water
(in addition to the 110,000 acre-feet currently
available) could be needed to provide full VAMP
test flow conditions at Vernalis. It was assumed
in this analysis that all of the supplemental water
would be obtained from either the Tuolumne or the
Merced river. Water could be obtained from both
rivers in any particular year but would not exceed
47,000 acre-feet in total.
4.2.1 Key Impact Issues
and Evaluation Criteria
To evaluate the effects of supplying supplemental
water for VAMP on water deliveries, carry-over storage,
and flows/water quality, two key parameters are
analyzed: changes in carry-over storage and changes
in river flows. These represent the major water
supply parameters affected by implementation of
the Project alternatives. Because of the way in
which "double-step" years are calculated,
they would only occur when either the existing year
or the previous year is relatively above normal
in wetness. Analysis records that carry-over storage
would be available.
Key issues considered in this analysis are:
- Effects on water deliveries to current water
users in the affected districts
- Changes in carry-over storage in New Don Pedro
Reservoir and Lake McClure
- Flow changes in the Merced and Tuolumne rivers
- Impact on the New Melones Projects ability
to meet water quality objectives at Vernalis,
including the impacts associated with a different
release pattern/timing of releases caused by the
acquisition of additional water on the tributaries
For carry-over storage, changes of less than 10
percent (between the Proposed Action and No Action)
are considered less than significant.
4.2.2 Analysis/Modeling
Methodology
The full hydrologic analysis is provided in Appendix
A. This analysis was conducted to evaluate a range
of potential hydrologic effects attributable to
the Proposed Project/Action on the Tuolumne and
Merced rivers. Two operational settings were developed:
No Action and the Proposed Project/Action.
- The No Action Alternative represents existing
hydrology and operations within the Bay-Delta
watershed, including the CVP and SWP meeting the
1995 WQCP and Biological Opinions on Winter-run
Chinook salmon and Delta Smelt. This alternative
also includes the current implementation of Water
Right Decision 1641 (State Board 1999) inclusive
of the San Joaquin River Agreement (SJRA) as capped
by the provision of up to 110,000 acre-feet of
VAMP water. Operations for the San Joaquin River
include Reclamation operating New Melones Reservoir
to the Interim Plan of Operation (Reclamation
1997b).
- The Proposed Project/Action Alternative represents
the performance of the SJRA if, during VAMP double-step
years, the full amount of water is provided to
achieve the VAMP Target Flow. The hydrology of
the Proposed Project/Action (up to 47,000 acre-feet
of supplemental water) is evaluated against the
hydrologic setting of the current implementation
of the SJRA (the No Action setting).
The SJRA has a term of 12 years (unless extended);
however, the hydrologic character of the 12 years
cannot be predicted. To evaluate the range of conditions
and hydrologic impacts that may occur, the Proposed
Action is evaluated using the long-term hydrologic
sequence of the period 1922 through 1992. Within
that period of historical record, various sequences
of hydrologic events occurred ranging from flood
to extended periods of drought. During this modeled
period, there are many years when the Proposed Action
is not needed, since the VAMP Target Flow can be
achieved with the current implementation of the
SJRA. During approximately 10 percent of the historical
record, the Proposed Action is needed. Details of
the modeling methodology are provided in Appendix
A.
4.2.2.1 Operation Simulation
Models
The hydrologic analysis (Appendix A) was based
on the most up-to-date models available in November
2000. This analysis relied on the interface of three
hydrologic models to simulate the potential hydrologic
effects of the Proposed Project/Action, SANJASM,
STNMODAM (Stanislaus Operations Model), and PROSIM.
San Joaquin Area Simulation Model (SANJASM)
Reclamations SANJASM model provided the simulation
of the San Joaquin River upstream of the confluence
of the Stanislaus River, including the hydrology
of west-side San Joaquin Valley CVP deliveries.
Stanislaus Operations Model (Modified Version)
A modified version of Reclamations STNMODAM
spreadsheet model provided the simulation of Stanislaus
River operations under assumptions of Reclamations
Interim Plan of Operation for New Melones.
Projects Simulation Model (PROSIM)
Reclamations PROSIM provided the simulation
of the CVP and SWP, and the Bay-Delta.
Within the context of the two alternatives, the
No Action and Proposed Project/Action, eight simulations
were performed. The model uses average monthly hydrologic
data and a monthly time-step. Although the VAMP
31-day test flow period could be established anytime
during the April through May period, the No Action
and the Proposed Action were each assumed to occur
during the entire month of April or
May. Two simulations were therefore needed to determine
the required VAMP Target Flows, one for the April
pulse flow assumption and a second for the May pulse
flow assumption. Similarly, two simulations were
needed to model the No Action Alternative incorporating
the provision of up to 110,000 acre-feet of VAMP
flow. Another four simulations represent the scenario
where the entire supplemental flow (up to 47,000
acre-feet in excess of the 110,000 acre-feet) originates
entirely from the Tuolumne River or
entirely from the Merced River, either occurring
in April or May.
4.2.2.2 Modeling Assumptions
No Action Alternative
The No Action Alternative is the same as existing
conditions. Before simulating the No Action Alternative,
the VAMP Target Flows were determined. After determining
the VAMP Target Flow levels, the flow division among
the members was estimated based on a series of procedures
discussed in the hydrology analysis (Appendix A).
This provided the basis for comparison with the
Proposed Action.
4.2.2.3 Modeling Assumptions
Proposed Action Setting
After determining the water to be provided by the
San Joaquin River Group Authority members under
the basic provisions of the SJRA (No Action, which
represents existing conditions), supplemental VAMP
releases required in excess of 110,000 acre-feet
were modeled.
For the model runs assuming that up to 47,000 acre-feet
of supplemental water would originate from the Tuolumne
River, it was assumed that the MID and TID provided
additional stream releases, in this case from New
Don Pedro Dam and passed at La Grange Dam. This
release would be an increase in flow above the release
that would otherwise be made in the absence of the
Proposed Project/Action (i.e., the release occurring
in the No Action setting).
For the model runs assuming that up to 47,000 acre-feet
of supplemental water would originate from the Merced
River, it was assumed that increased stream releases
would come from Lake McClure/New Exchequer Dam.
This release would be an increase in flow above
the release that would otherwise be made in the
absence of the Proposed Project/Action.
4.2.3 Environmental Impacts
and Mitigation
This section evaluates the effects of the releases
on the Tuolumne and Merced rivers on water deliveries,
carry-over storage, and changes in flow and water
quality on the San Joaquin River. The potential
impact of the Proposed Project/Action manifests
as reduced storage in New Don Pedro and/or New Exchequer
Reservoirs until such time that the storage is recovered
through reductions and releases from the reservoirs
that would otherwise be in excess of instream flow
requirements. The Proposed Project/Action is not
anticipated to affect the diversion or delivery
of water to any water user within the affected basins;
therefore, no change to the timing or occurrence
of return flows is anticipated. Table
4-1 presents a summary of the changes in flow
and reservoir storage for both the April and May
conditions on the Tuolumne and Merced rivers, based
on the data contained in the hydrology analysis
(Appendix A).
4.2.3.1
Water Deliveries
MID, TID, and the Merced ID make
water deliveries to agricultural and municipal/industrial
users.
No Action
Water deliveries under the No Action Alternative
would be the same as existing conditions. Water
that could be used for the supplemental up to 47,000
acre-feet would remain in storage until released
at a future date for hydroelectric purposes, agriculture,
municipal and industrial, fish, spills, or flood
control.
Table
4-1
Summary of Predicted Changes in Flow for the Tuolumne
and Merced Rivers and Impacts to New Melones Reservoir
from A 71-Year Hydrologic Model Analysis of VAMP
Conditions
Proposed Action
All of the up to 47,000 acre-feet of supplemental
water would come from carry-over storage. Water
deliveries provided under the existing VAMP operations
would not change. No impact to water deliveries
would occur in the MID, TID, and Merced ID service
areas.
4.2.3.2
Carry-over Storage in San Joaquin Basin Reservoirs
Carry-over storage is the amount of water retained
in a reservoir at the end of September of each water
year. The amount of water dedicated to carry-over
storage is balanced against the amount needed to
meet immediate delivery needs, hydropower generation
needs, and instream flow requirements of a project,
according to operation rules that differ for each
reservoir (State Board 1998).
To determine the changes that would occur due to
implementing the Project alternatives on carry-over
storage, September end-of-month storage for the
Proposed Project are compared to the No Action Alternative.
No Action
The No Action Alternative represents
existing conditions. There would be no change in
carry-over storage in the two reservoirs that are
the source of supply, and no changes would take
place in New Melones Reservoir.
Proposed Action
Implementing the Proposed Action
would affect carry-over storage in the reservoirs
within the Project Area. These changes are described
below.
Tuolumne River. During years
when supplemental water is required (either April
or May), an increase in releases to the lower Tuolumne
River occurs and a corresponding decrease in New
Don Pedro Reservoir storage results during the pulse
flow. In most instances the additional water released
is recovered in storage in the following year by
a reduction in releases that would otherwise be
in excess of minimum Tuolumne River flow requirements.
In two instances (e.g., the May 1946 and April 1959
supplemental releases), recovery does not occur
for several years.
The changes in carry-over storage in New Don Pedro
Reservoir for the April and May releases are shown
on Figure 4-1. There would be a decrease in carry-over
storage in New Don Pedro Reservoir in about 18 to
20 percent of the 71 years simulated. When supplemental
water is needed for April releases, the maximum
change in carry-over storage would be a decrease
of less than 35,000 acre-feet. For May releases,
the maximum change would be a decrease of 45,000
acre-feet. Figure 4-2 shows the same results but
as a percentage of the storage under the No Action
scenario. The worst case during the 71-year simulation
period was a 5 percent decrease that occurred only
once. For most years when supplemental water is
needed, the decrease in carry-over storage would
be less than 3 percent. The impacts to carry-over
storage are considered less than significant, given
that they are expected to be relatively minor, infrequent,
and short term in duration.
Merced River. During the years when supplemental
water is required, an increase in releases to the
lower Merced River occurs and a corresponding decrease
in Lake McClure/New Exchequer Reservoir storage
results. In one modeled circumstance (May 1970 and
May 1971 supplemental water), a reduction in storage
accumulated due to the sequential provision
of supplemental water. In most instances the additional
water released would be recovered in storage in
the following year by a reduction in releases that
would otherwise be in excess of minimum Merced River
flow requirements. In two instances (e.g., 1959
and 1971 April supplemental release), recovery did
not occur until one or more years later.
The change in carry-over storage in Lake McClure
for the April and May releases is shown on Figure
4-3. There would be a decrease in carry-over storage
in about 17 to 20 percent of the years simulated.
When supplemental water would be needed, for April
releases, the maximum change in carry-over storage
would be a decrease of less than 35,000 acre-feet.
For May the maximum change would be a decrease of
about 50,000 acre-feet. Figure 4-4 shows the same
results but as a percentage of the storage under
the No Action scenario. The worst case during the
71-year simulation period was a 17 percent decrease,
which occurred only once in 1971. In about 2 to
3 percent of the years, there would be a decrease
in carry-over storage of greater than 10 percent.
For most years when supplemental water is needed,
the decrease in carry-over storage would be less
than 10 percent. The impacts to carry-over storage
would be less than significant, given that they
are expected to be relatively minor, infrequent,
and short term in duration.
4.2.3.3
Changes in Flow and Water Quality
Table 4-2 shows the years where supplemental Spring
Pulse Flows above 110,000 acre-feet were needed
and the amount of supplemental water required. Supplemental
flows were necessary in approximately 10 percent
of the years during the modeled period 1922 through
1992.
The above amounts of supplemental water were modeled
as coming from either the Tuolumne River or from
the Merced River (the Proposed Action). Results
of that modeling in comparison to No Action are
summarized below.
Table 4-2
VAMP Supplemental Water (1,000 acre-feet)
|
April VAMP Period
|
May VAMP Period
|
|
Year
|
Total VAMP
Water
|
Supplemental
Portion
|
Year
|
Total VAMP
Water
|
Supplemental
Portion
|
|
1944
|
116
|
6
|
1936
|
126
|
16
|
|
1959
|
145
|
35
|
1939
|
150
|
40
|
|
1966
|
117
|
7
|
1944
|
156
|
46
|
|
1968
|
140
|
30
|
1946
|
125
|
15
|
|
1971
|
130
|
20
|
1966
|
140
|
30
|
|
1981
|
129
|
19
|
1970
|
127
|
17
|
|
1984
|
112
|
2
|
1971
|
145
|
35
|
| |
1984
|
146
|
36
|
Click Image
to enlarge

Tuolumne River Providing Supplemental Water
For the April supplemental flow setting, the change
in flow regime within the Tuolumne River system
does not affect operations of the Merced River or
the Stanislaus River. Changes within the Tuolumne
River occur during periods when Stanislaus River
operations are not controlled by Vernalis flow or
quality objectives, and a change of Tuolumne River
operations outside of the month of the VAMP (April-May)
would not affect Merced River operations.
Identical to the April supplemental flow setting,
the May setting for Tuolumne River providing the
supplemental flow would not affect Merced River
operations. However, for the May supplemental water
setting, the hydrologic analysis (Appendix A) indicates
that Stanislaus River operations may be affected
by the recovery of New Don Pedro Reservoir storage
in one instance (1985) out of the 8 years requiring
supplemental flow in May, which is within the 71
years of modeled sequential hydrology. In this instance,
the reduction in release to the Tuolumne River during
April 1985 (for recovery of the May 1984 supplemental
water) resulted in an increased release from New
Melones for water quality objectives at Vernalis.
In other words, the Proposed Action could result
in a short-term need to increase releases from New
Melones Reservoir to meet water quality objectives
at Vernalis. The effect on the river and to New
Melones operations would be less than significant.
The modeling results represent that the May 1984
supplemental water release may affect water quality
in 1985 at Vernalis. Due to the amount of water
that is available for water quality releases in
the modeled year of 1985, under the New Melones
Interim Plan of Operation, the April 1985 water
quality release described above came at the expense
of being able to fully meet water quality objectives
in the following July 1985. Sufficient water exists
in New Melones Reservoir to fully comply with the
water quality objective. Based on the 71-year hydrologic
sequence, this impact would be highly unlikely to
occur and is less than significant. Should it occur,
Reclamation has the capability to mitigate the potential
impact with New Melones Operations.
Merced River Providing Supplemental Water
For the April or May supplemental flow setting,
the change in flow regime within the Merced River
system would not affect operations of the Tuolumne
River. Also, for the May supplemental flow setting,
changes within the modeled Merced River flow regime
would occur during periods when Stanislaus River
operations are not controlled by Vernalis flow or
quality objectives; therefore, no changes to the
Stanislaus River operation would occur. There would
be no impact to water quality from the flow changes.
For the April supplemental water setting, modeling
indicates that Stanislaus River operations may be
affected by the recovery of Lake McClure/New Exchequer
Reservoir storage resulting from the modeled year
1971 supplemental release. In this instance, the
supplemental release in the modeled year 1971 resulted
in a reduction in release to the Merced River during
August 1973. This reduction in summertime discretionary
release from Lake McClure resulted in an increased
release from New Melones for water quality objectives
at Vernalis. The impact occurred only once during
the 71-year period. The probability that this impact
would occur during the 2001-2010 period is very
low. This increased release from New Melones in
modeled year 1973 resulted in a minor reduction
in spill to the Stanislaus River in March 1975.
Any changes to New Melones operations due to the
Proposed Action are expected to be infrequent, minor,
and short term in duration. Consequently, the impact
is less than significant.
4.2.4 Impact Summary and
Mitigation of Impacts
4.2.4.1 Water Deliveries
Proposed Action
- Tuolumne River: There would be no changes in
water deliveries relative to the No Action scenario,
so there is no impact.
- Merced River: There would be no changes in water
deliveries relative to the No Action scenario,
so there is no impact.
4.2.4.2 Water Storage
Proposed Action
- Tuolumne River: Implementation of the Proposed
Action could result in reduced carry-over storage
in Don Pedro Reservoir between 15 and 20 percent
of the 71 years analyzed. However, the decrease
in carry-over storage would generally be less
than 3 percent and would always be less than 10
percent. This would be a less-than-significant
impact, and no mitigation is required.
- Merced River: Implementation of the Proposed
Action could result in reduced carry-over storage
in Lake McClure greater than 10 percent in about
2 to 3 percent of the 71-year period. For most
of the period when supplemental water is needed,
the decrease in carry-over storage would be less
than 10 percent. The impact would be less than
significant, and no mitigation is required.
4.2.4.3 Water Quality
Proposed Action
- Tuolumne River: Maintaining compliance with
the water quality objective at Vernalis was impacted
in only one instance (July 1985) due to release
of the supplemental water (in May 1984) during
the 71-year simulation period. In the context
of a hydrologic sequence, the probability of this
event occurring over the 2001-2010 period is very
small, and it is considered less than significant.
- Merced River: In one instance, the supplemental
water release in April 1971 resulted in an increased
release from New Melones Reservoir in August 1973
in order to meet the water quality objective at
Vernalis. This release resulted in a minor reduction
in spill to the Stanislaus River. Any changes
to New Melones operations due to the Proposed
Action are considered less than significant.
Final SEIS/EIR
CH 4 |
March 13, 2001
|
|